Process Number: 233 |
Revision Date: 3/7/2005 4:04:25 PM |
Revision #: 0 |
MIS Staff Data Preparation
Office Responsible: | DPAY - District - Payroll | Process Type: | internal |
Position Title: | Payroll Specialist | Author: | cgamboa | ||
Cross Trained Staff: | Manager: | AOntiveros | Vice Pres.: | btemple |
Timeline (Deadlines or Time-Constraints) : |
MIS Data Submissions Timeline |
What must be done before this process is started: |
On County system: Additional Earnings Data Input. On Datatel: stafdnld.out file in /home/datatel/cgamboa directory. |
Which processes are waiting for this process: |
MIS Term End submission (due Nov 1). MIS Fall Data Collection (due 30 days). |
Source documents or communication with information needed for this process: |
What is the end-result of this process, or the hand-off |
Inform DCS the following files are available, to proceed with MIS submission: STAFEB72 (demographics) is created for both fall collection and term end submission. STAFEJ72 (assignments) is created for fall collection only; have DCS prepare an Excel file (using PARSE.EJ) for HR review before submission. FACXE72 is created at term end only. |
What steps must be taken independent of the computer system (Manual Process) |
Which steps must be taken on a computer (Electronic Process): |
Define term on COTTUP. Upload data to County using COFAUP, COFALD. Resolve load errors on County system. Resolve MIS errors (COSDIN). Download data to Datatel directory. |
Related Documents to Process (e.g. Datatel documentation, Government code books, etc.) |
Chancellor`s website (cccco.org) CECC HR Manual / Staff Data Reporting |
Notes (Cautions, suggestions for improvement, etc.) |
Automate Additional Earnings Data Input. |
Process Number: 233 |
Revision Date: 3/7/2005 4:04:25 PM |
Revision #: 0 |