The below list is the result of a collaborative effort on the part of the campuses and the Facilities Planning & Construction department, along with input from industry professionals. It takes into consideration SBCCD’s mission and goals to serve more students and address major health/life/safety issues associated with existing facilities.
SBCCD Bond Construction Project List
Project Name | Campus | Total Project Budget | Delivery Method |
** CC01-3601 Technical Building Replacement (Career Pathway 1) | SBVC | $101.M | DBB |
CC01-3603 M&O Repurposing | SBVC | $1.5M | DBB |
** CC01-3605 Softball Field | SBVC | $6.2M | DBB |
CC01-3606 Student Services Building | SBVC | $104.7M | D/B |
CC01-3607 Administration & Campus Center Repurposing | SBVC | $8.8M | D/B |
** CC01-3608 Career Pathways Phase 2 | SBVC | $86.7M | D/B |
CC01-3609 Physical Sciences & Health and Life Science | SBVC | $4.4M | DBB |
CC01-3610 SBVC Campus-Wide Infrastructure (Approx. 20 sub-projects) | SBVC | $42.9M | DBB |
** CC01-3610-01 Piping | SBVC | $74,988 | DBB |
** CC01-3610-02 Library Roof | SBVC | $1M | DBB |
** CC01-3610-03 Landscape (Arborist) | SBVC | $39,520 | DBB |
** CC01-3610-04 Planetarium HVAC Replacement | SBVC | $1.4M | DBB |
** CC01-3610-05 Warehouse M&O Building | SBVC | $36,882 | DBB |
CC01-3610-06 Physical Science & Health Life Science Building - Mechanical Improvements | SBVC | $3.1M | DBB |
** CC01-3610-07 Utility Upgrades (Earthquake Valves & Electrical Submeters) | SBVC | $910,000 | DBB |
CC01-3610-08 East Wing Mechanical Improvements | SBVC | $4.6M | DBB |
** CC01-3610-09 Old Central Plant Repurpose | SBVC | $2.24M | DBB |
** CC01-3610-10 Campus Roof Replacement | SBVC | $1.9M | DBB |
CC01-3610-12 Security Upgrades | SBVC | $4.5M | DBB |
CC01-3610-14 Greek Theater Shade Structure | SBVC | $1.8M | DBB |
CC01-3610-15 Business Quad Development | SBVC | $3.5M | DBB |
** CC01-3610-16 Fiber Optic Termination & Testing | SBVC | $1.1M | DBB |
** CC01-3610-17 Planetarium Flooring R&R | SBVC | $40,000 | DBB |
** CC01-3610-18 Gym Lobby Flooring R&R | SBVC | $840,108 | DBB |
CC01-3610-20 Perimeter Fencing | SBVC | $1.4M | DBB |
CC01-3610-21 KVCR Improvements | SBVC | $1M | DBB |
CC01-3610-22 East Wing Improvements Phase 2 | SBVC | $3M | DBB |
CC01-3610-24 Biology Garden Expansion | SBVC | $900,000 | DBB |
CC02-3621 Crafton Hall Renovation | CHC | $4.1M | DBB |
CC02-3624 Student Support Building Renovation (SSB) | CHC | $433,000 | DBB |
** CC02-3623 Gymnasium Demolition | CHC | $1.7M | DBB |
** CC02-3625 East Valley Public Training Center (EVPSTC) | CHC | $11.8M | D/B |
CC02-3631 Instructional Building | CHC | $54.3M | D/B |
** CC02-3633 Central Complex 2 Renovation (CC2) | CHC | $13.3M | D/B |
** CC02-3634 Child Development Center Renovation (CDC) | CHC | $3.8M | DBB |
** CC02-3635 New Performing Arts Center Building (PAC) | CHC | $54.5M | DBB |
CC02-3626 CHC Campus-Wide Infrastructure (Approx. 20 sub-projects) | CHC | $20M | DBB & D/B |
** CC02-3626-01 Exterior Lighting Improvements | CHC | $1M | DBB |
** CC02-3626-02 Campus Wide Irrigation Upgrades | CHC | $492,000 | DBB |
** CC02-3626-03 Campus Accessibility and Site Improvements | CHC | $1.6M | DBB |
** CC02-3626-04 Central Plane Controls Upgrades & Chillers | CHC | $736,000 | DBB |
** CC02-3626-05 Landscape (Arborist) | CHC | $37,000 | DBB |
CC02-3626-06 Replacement of Existing Cooling Towers | CHC | $1.3M | DBB |
CC02-3626-07 Wayfinding Signage | CHC | $68,000 | DBB |
CC02-3626-08 Campus Wide Security | CHC | $2.7M | D/B |
CC02-3626-10 New Metering | CHC | $1.2M | DBB |
CC02-3626-11 New Gas Submeters | CHC | $69,000 | DBB |
CC02-3626-12 Existing PMO Office Data/Cable Upgrades | CHC | $5,000 | DBB |
** CC02-3626-14 LRC Generator & Equipment Upgrades | CHC | $711,000 | DBB |
** CC02-3626-16 Building 17 Water Main Repair | CHC | $17,000 | DBB |
CC02-3626-17 M&O Office Trailer Upgrades | CHC | $7,500 | DBB |
CC02-3626-18 Facilities Master Plan Addendum | CHC | $34,700 | DBB |
** CC02-3626-19 Solar PV | CHC | $8.1M | D/B |
CC02-3626-20 BL 10 Third Floor Corridor Door Upgrade | CHC | $122,000 | DBB |
CC02-3626-21 CCR Multi-Purpose Room Acoustical Improvements | CHC | $136,000 | DBB |
** Designates project has been completed or procurement has been completed